Aetna Casualty And Surety Co. v. Aniero Concrete Co.

404 F.3d 566 | Court of Appeals for the Second Circuit | 2005

enforcedCited 106 timesFLAGSHIPTexas
View on Court Website

What This Case Means for Subcontractors

Aniero Concrete challenged a construction contract completion agreement after the School Construction Authority (SCA) refused to consent to assignment of the contract. The court ruled the contract was invalid because a required condition—the SCA's written consent to assignment—was never satisfied. This decision means that even if you've done the work and other contract terms seem favorable, a contract can be completely unenforceable if a critical condition precedent isn't met. For subcontractors, this is a critical reminder that assignment restrictions and consent requirements in prime contracts can kill your payment rights downstream.

Key Takeaways

  • Always verify that any required consents or approvals from the project owner are obtained in writing before relying on a contract—missing this can void the entire agreement
  • If your contract requires assignment consent, get it documented before you start work or assign your rights; don't assume verbal approval or partial performance counts
  • Review your subcontract for any conditions precedent (like owner approval, insurance requirements, or lien waivers) and confirm they're satisfied before you're owed payment

The Completion Agreement was invalid due to an unsatisfied express condition precedent.

Court of Appeals for the Second Circuit, 2005

Frequently Asked Question

Can I get paid if the prime contractor assigned the work to me without the owner's written consent?

Not necessarily. If the contract requires the owner's written consent to assignment and that consent was never obtained, the entire contract may be invalid—even if you completed the work. Always require proof of written consent before starting work on an assigned contract. Don't rely on verbal approval or assumptions that the owner won't object.

Related Cases

Green International, Inc. v. Solis

1997modified

No-damages-for-delay clauses in construction contracts need not meet the conspicuousness requirement established in Dresser for exculpatory negligence clauses, and such clauses are enforceable to bar delay damages absent specific exceptions.

Italian Cowboy Partners, Ltd. v. Prudential Insurance Co. of America

2011remanded

A standard merger clause without clear and unequivocal language expressly disclaiming reliance does not bar a fraud claim, even in a commercial lease agreement between parties.

Department of the Army v. Blue Fox, Inc.

1999voided

Sovereign immunity bars subcontractors from enforcing equitable liens against the United States Government, as the APA's waiver of immunity does not extend to claims for money damages.

Rocor International, Inc. v. National Union Fire Insurance Co. of Pittsburgh

2002modified

An insured may assert an article 21.21 claim against its excess liability carrier for unfair claim settlement practices, but liability requires proof of a proper settlement demand within policy limits that an ordinarily prudent insurer would accept.

Weize Co. v. Colorado Regional Construction, Inc.

2010affirmed

A general contractor violated Colorado's construction trust fund statute by failing to hold funds in trust for subcontractors and suppliers, and a lien release bond does not exempt contractors from trust fund obligations or excuse failure to record a lis pendens.

EBC, Inc. v. Clark Building System, Inc.

2010enforced

A supplier cannot enforce a payment obligation against a project owner based on a letter offering optional direct payment arrangements, where the supplier's own deposition testimony demonstrates it never understood the letter as a binding contract.