All Seasons Window & Door Manufacturing, Inc. v. Red Dot Corp.

181 S.W.3d 490 | Texas Court of Appeals, 6th District (Texarkana) | 2005

modifiedCited 46 timesBATTLE_TESTEDTexas
View on Court Website

What This Case Means for Subcontractors

All Seasons hired Red Dot to build a metal building but withheld the final payment over a $5,000 dispute about construction delays and quality. The trial court ordered All Seasons to pay Red Dot $143,800 plus interest, but disagreed on the interest rate. The appeals court ruled that the contract allowed 18% interest (the legal maximum), not 10%, and that interest started accruing when construction finished in October 2001. This matters because it shows courts will enforce maximum legal interest rates in construction contracts and won't let payment disputes excuse full payment obligations.

Key Takeaways

  • Include explicit interest rate language in your contracts—if you don't specify a rate, courts may apply the legal maximum (18% in Texas), which could work against you if you're the one owing money
  • Withholding final payment over a partial dispute can backfire; you'll likely owe the full amount plus interest and attorney's fees, making the dispute far more expensive
  • Interest accrues from the date work is completed, not from the date of dispute or lawsuit, so delays in resolving claims cost you money

The contractual interest rate should have been eighteen percent, not ten percent.

Texas Court of Appeals, 6th District (Texarkana), 2005

Frequently Asked Question

What interest rate will a court apply if my construction contract doesn't specify one?

In Texas, courts will apply the maximum legal interest rate allowed by law, which is 18%. Interest starts accruing from the date work is completed, not when a dispute arises. To avoid surprises, always specify your interest rate clearly in the contract.

Related Cases

Atlantic Marine Constr. Co. v. United States Dist. Court for Western Dist. of Tex.

2013reversed

Forum-selection clauses in federal contracts are enforced through §1404(a) transfer motions, not §1406(a) dismissals, and must be given controlling weight except in exceptional circumstances.

Texas Natural Resource Conservation Commission v. IT-Davy

2002voided

Sovereign immunity bars a contractor's breach-of-contract suit against a state agency absent express legislative consent; neither the agency's conduct, contract terms, nor general statutes waive immunity from suit.

Martin K. Eby Construction Company, Inc. v. Dallas Area Rapid Transit

2004enforced

A contractor must exhaust administrative remedies established by a regional transportation authority before pursuing breach of contract claims in court, even when the authority lacks governmental immunity from suit.

Edwin P. Harrison, and United States of America, Party in Interest v. Westinghouse Savannah River Company

1999reversed

The Fourth Circuit reversed the district court's dismissal, holding that the False Claims Act broadly reaches false statements made to obtain government contract approval, not just false payment claims themselves.

General Services Commission v. Little-Tex Insulation Co.

2001voided

The State does not waive sovereign immunity from breach-of-contract suits by accepting contract benefits; Chapter 2260's administrative procedure is the exclusive remedy for such claims.

Green International, Inc. v. Solis

1997modified

No-damages-for-delay clauses in construction contracts need not meet the conspicuousness requirement established in Dresser for exculpatory negligence clauses, and such clauses are enforceable to bar delay damages absent specific exceptions.