Argee Corp. v. Solis

932 S.W.2d 39 | Texas Court of Appeals, 9th District (Beaumont) | 1995

modifiedCited 18 timesSTANDARDTexas
View on Court Website

What This Case Means for Subcontractors

Argee Corp. hired Solis as a subcontractor for steel and concrete work on three Texas prison projects. Argee failed to pay Solis on time, forcing Solis to abandon two projects. The court ruled that because Argee breached the payment obligation first, Solis was excused from following strict procedural requirements in the contract (like formal change order procedures) and could recover damages. This means a contractor cannot hide behind contract technicalities when they're the one who broke the deal.

Key Takeaways

  • If your general contractor fails to pay you on time, you may be excused from following strict procedural deadlines in the contract—don't let them use technicalities against you after they breach.
  • Document all non-payment issues and your attempts to continue work despite lack of payment; this evidence supports your claim that the GC's breach forced you to stop.
  • A breaching party loses the right to enforce procedural requirements for claims and change orders—focus on proving the GC's payment failure, not on whether you followed every procedural step.

A breaching party relinquishes its contractual procedural rights concerning claims for additional costs.

Texas Court of Appeals, 9th District (Beaumont), 1995

Frequently Asked Question

If my general contractor doesn't pay me, can they claim I violated contract procedures?

No. Texas courts have ruled that when a general contractor breaches by failing to pay, they lose the right to enforce strict procedural requirements against you. Your failure to follow procedures is excused by their breach. Focus on proving non-payment and documenting your damages.

Related Cases

Texas Natural Resource Conservation Commission v. IT-Davy

2002voided

Sovereign immunity bars a contractor's breach-of-contract suit against a state agency absent express legislative consent; neither the agency's conduct, contract terms, nor general statutes waive immunity from suit.

Martin K. Eby Construction Company, Inc. v. Dallas Area Rapid Transit

2004enforced

A contractor must exhaust administrative remedies established by a regional transportation authority before pursuing breach of contract claims in court, even when the authority lacks governmental immunity from suit.

Edwin P. Harrison, and United States of America, Party in Interest v. Westinghouse Savannah River Company

1999reversed

The Fourth Circuit reversed the district court's dismissal, holding that the False Claims Act broadly reaches false statements made to obtain government contract approval, not just false payment claims themselves.

Green International, Inc. v. Solis

1997modified

No-damages-for-delay clauses in construction contracts need not meet the conspicuousness requirement established in Dresser for exculpatory negligence clauses, and such clauses are enforceable to bar delay damages absent specific exceptions.

Italian Cowboy Partners, Ltd. v. Prudential Insurance Co. of America

2011remanded

A standard merger clause without clear and unequivocal language expressly disclaiming reliance does not bar a fraud claim, even in a commercial lease agreement between parties.

Heldenfels Bros. v. City of Corpus Christi

1992enforced

A municipality owes no duty to a subcontractor to ensure a general contractor provides valid payment bonds, and a subcontractor cannot recover from the municipality under quantum meruit, unjust enrichment, or negligence theories when the general contractor abandons the project.