Conam Alaska v. Bell Lavalin, Inc.

842 P.2d 148 | Alaska Supreme Court | 1992

enforcedCited 60 timesBATTLE_TESTEDTexas
View on Court Website

What This Case Means for Subcontractors

Conam Alaska, a subcontractor on a North Slope project, sued Bell Lavalin for breach of contract and professional negligence. The court ruled that Conam's failure to perform was excused because Bell Lavalin breached its duty to grant a time extension. While the jury awarded contract damages to Conam, the court rejected the professional negligence claim due to insufficient proof of causation. The key lesson: a prime contractor cannot terminate a subcontractor for nonperformance if the prime itself caused the delay through breach.

Key Takeaways

  • Document all requests for time extensions in writing. If the prime denies or ignores your extension request, you have a defense against termination for delay.
  • Contract damages are easier to prove than professional negligence damages. Focus on quantifying direct losses (labor, equipment, overhead) rather than pursuing negligence claims.
  • A 'total breach' is required to justify termination. Partial breaches or isolated failures do not give the prime the right to terminate your subcontract.

Termination is justified only in the event of a total breach.

Alaska Supreme Court, 1992

Frequently Asked Question

Can I be terminated for missing a deadline if the prime contractor refused to give me a time extension?

No. If you requested a time extension and the prime contractor breached its duty to grant one, your nonperformance is excused. You may also recover contract damages. However, you must document the request and the prime's refusal in writing to prove this defense.

Related Cases

Gall v. United States

2007enforced

Appellate courts must review all sentences under an abuse-of-discretion standard regardless of whether they fall inside or outside the Guidelines range, and cannot require extraordinary circumstances to justify sentences outside the range.

Texas Natural Resource Conservation Commission v. IT-Davy

2002voided

Sovereign immunity bars a contractor's breach-of-contract suit against a state agency absent express legislative consent; neither the agency's conduct, contract terms, nor general statutes waive immunity from suit.

Piotrowski v. City of Houston

2001reversed

Municipal liability under § 1983 requires proof of official policy as the moving force; isolated employee misconduct insufficient, and equal protection claim time-barred.

Adarand Constructors, Inc. v. Pena

1995remanded

Federal race-based classifications must be analyzed under strict scrutiny regardless of whether they benefit or burden minorities, and the Fifth Amendment's equal protection obligation equals the Fourteenth Amendment's.

Northeastern Florida Chapter of the Associated General Contractors of America v. City of Jacksonville

1993remanded

An association of contractors has standing to challenge a minority set-aside ordinance without proving any member would have won a contract absent the ordinance; the injury is denial of equal competitive opportunity, not loss of a specific contract.

Martin K. Eby Construction Company, Inc. v. Dallas Area Rapid Transit

2004enforced

A contractor must exhaust administrative remedies established by a regional transportation authority before pursuing breach of contract claims in court, even when the authority lacks governmental immunity from suit.