Daniel E. Terreri & Sons, Inc. v. Mahoning County Board of Commissioners

786 N.E.2d 921 | Ohio Court of Appeals | 2003

reversedCited 33 timesBATTLE_TESTEDTexas
View on Court Website

What This Case Means for Subcontractors

Mahoning County hired Terreri Construction and Avila Supply for two renovation contracts on the Higbee building. The county delayed issuing the notice to proceed, and the contractors demanded payment for the delay. The court ruled that 'no damages for delay' clauses in the contracts protected the county from liability, and the contractors' demand letters amounted to breaking the contract themselves. The judgment against the contractors was reversed.

Key Takeaways

  • A 'no damages for delay' clause can shield the owner from paying contractors for project delays, even if the owner causes them. Read your contract carefully before signing.
  • Sending a demand letter threatening to walk off the job can be seen as you breaking the contract first, which eliminates your right to sue. Consult a lawyer before making threats.
  • Performance bonds and bid guarantees don't protect you if the contract has strong 'no damages for delay' language. Negotiate these clauses before bidding.

Appellants were protected by the 'no damages for delay' provisions in the two contracts.

Ohio Court of Appeals, 2003

Frequently Asked Question

Can I get paid if the owner delays giving me the notice to proceed?

Not if your contract has a 'no damages for delay' clause. This clause typically bars contractors from recovering money for owner-caused delays. You must negotiate or remove this language before signing, or accept the risk of unpaid waiting time.

Related Cases

Atlantic Marine Constr. Co. v. United States Dist. Court for Western Dist. of Tex.

2013reversed

Forum-selection clauses in federal contracts are enforced through §1404(a) transfer motions, not §1406(a) dismissals, and must be given controlling weight except in exceptional circumstances.

Texas Natural Resource Conservation Commission v. IT-Davy

2002voided

Sovereign immunity bars a contractor's breach-of-contract suit against a state agency absent express legislative consent; neither the agency's conduct, contract terms, nor general statutes waive immunity from suit.

Martin K. Eby Construction Company, Inc. v. Dallas Area Rapid Transit

2004enforced

A contractor must exhaust administrative remedies established by a regional transportation authority before pursuing breach of contract claims in court, even when the authority lacks governmental immunity from suit.

General Services Commission v. Little-Tex Insulation Co.

2001voided

The State does not waive sovereign immunity from breach-of-contract suits by accepting contract benefits; Chapter 2260's administrative procedure is the exclusive remedy for such claims.

Green International, Inc. v. Solis

1997modified

No-damages-for-delay clauses in construction contracts need not meet the conspicuousness requirement established in Dresser for exculpatory negligence clauses, and such clauses are enforceable to bar delay damages absent specific exceptions.

Moncharsh v. Heily & Blase

1992enforced

An arbitrator's decision is generally not reviewable for errors of fact or law, with limited exceptions for fraud, corruption, exceeding powers, or procedural unfairness.