Davis Erection Co., Inc. v. Jorgensen

534 N.W.2d 746 | Nebraska Supreme Court | 1995

remandedCited 31 timesBATTLE_TESTEDTexas
View on Court Website

What This Case Means for Subcontractors

Davis Erection sued to collect money owed by Jorgensen, and tried to garnish (seize) payments that Eriksen Construction owed to Jorgensen. Eriksen claimed it didn't owe Jorgensen anything because it had the right to offset (subtract) its own claims against Jorgensen from what it owed. The Nebraska Supreme Court ruled that you cannot use a setoff unless you take clear action to claim it—like sending written notice or making entries in your books. The court reversed the lower court's decision and sent the case back for trial.

Key Takeaways

  • If you want to offset money owed to you against money you owe a contractor, you must document it in writing or in your records at the time you claim the setoff. Silence or informal agreement won't work.
  • Setoffs only work against money that is certain and due now. You cannot offset uncertain, future, or contingent claims (like potential damages or disputed change orders) against money you definitely owe today.
  • Keep contemporaneous written records of any setoff claims—emails, letters, or accounting entries dated when you first assert the right. This protects you if the debt is later collected through garnishment.

Setoff requires intent, action, and record evidencing exercise of the right.

Nebraska Supreme Court, 1995

Frequently Asked Question

Can I subtract what a contractor owes me from what I owe them without telling them?

No. To claim a setoff, you must take affirmative action—send written notice, make accounting entries, or create other documented evidence that you're exercising the setoff right. Simply withholding payment without notice is not enough. Also, you can only setoff claims that are certain and due now, not uncertain or future claims.

Related Cases

Texas Natural Resource Conservation Commission v. IT-Davy

2002voided

Sovereign immunity bars a contractor's breach-of-contract suit against a state agency absent express legislative consent; neither the agency's conduct, contract terms, nor general statutes waive immunity from suit.

Martin K. Eby Construction Company, Inc. v. Dallas Area Rapid Transit

2004enforced

A contractor must exhaust administrative remedies established by a regional transportation authority before pursuing breach of contract claims in court, even when the authority lacks governmental immunity from suit.

Edwin P. Harrison, and United States of America, Party in Interest v. Westinghouse Savannah River Company

1999reversed

The Fourth Circuit reversed the district court's dismissal, holding that the False Claims Act broadly reaches false statements made to obtain government contract approval, not just false payment claims themselves.

Green International, Inc. v. Solis

1997modified

No-damages-for-delay clauses in construction contracts need not meet the conspicuousness requirement established in Dresser for exculpatory negligence clauses, and such clauses are enforceable to bar delay damages absent specific exceptions.

Heldenfels Bros. v. City of Corpus Christi

1992enforced

A municipality owes no duty to a subcontractor to ensure a general contractor provides valid payment bonds, and a subcontractor cannot recover from the municipality under quantum meruit, unjust enrichment, or negligence theories when the general contractor abandons the project.

Flameout Design & Fabrication, Inc. v. Pennzoil Caspian Corp.

1999enforced

Summary judgment for defendants was properly granted because Flameout failed to satisfy the statute of frauds for an alleged three-year contract, as the three documents cited did not constitute a signed, enforceable written agreement for the sale of goods.