Driver Pipeline agreed to dig trenches and lay pipe for a 100-mile gas pipeline project on a tight 14-week schedule. Heavy rains slowed work significantly, and Driver fell behind and asked for extra time and money. The court found Driver did breach the contract by not meeting the deadline, but ruled that Mustang could not terminate the contract or recover damages because the breach wasn't material enough to justify those actions, and Mustang failed to prove its claimed damages were reasonable.
Just because you miss a deadline doesn't mean the owner can terminate your contract—the breach has to be 'material' (serious enough to defeat the purpose of the contract). A partial delay may not qualify.
Weather delays are a major risk. If your bid assumes no rain days, get that in writing and clarify whether the owner must grant extensions. Don't rely on vague contract language that says the owner 'may' give extra time.
The owner must prove damages are reasonable and necessary with actual evidence. Simply showing what they paid or charged is not enough to recover money from you.