Eastern Electric Corp. v. Shoemaker Construction Co.

657 F. Supp. 2d 545 | District Court, E.D. Pennsylvania | 2009

enforcedCited 59 timesBATTLE_TESTEDTexas
View on Court Website

Holding Summary

Court granted default judgment against owners for material breach of construction contracts by failing to pay invoices over 100 days past due, awarding damages including unpaid contract balances, interest, penalty interest, and delay claims under Pennsylvania law.

failure to make payments when due is material breach excusing contractor performance

District Court, E.D. Pennsylvania, 2009

Related Cases

Gall v. United States

2007enforced

Appellate courts must review all sentences under an abuse-of-discretion standard regardless of whether they fall inside or outside the Guidelines range, and cannot require extraordinary circumstances to justify sentences outside the range.

Texas Natural Resource Conservation Commission v. IT-Davy

2002voided

Sovereign immunity bars a contractor's breach-of-contract suit against a state agency absent express legislative consent; neither the agency's conduct, contract terms, nor general statutes waive immunity from suit.

Piotrowski v. City of Houston

2001reversed

Municipal liability under § 1983 requires proof of official policy as the moving force; isolated employee misconduct insufficient, and equal protection claim time-barred.

Adarand Constructors, Inc. v. Pena

1995remanded

Federal race-based classifications must be analyzed under strict scrutiny regardless of whether they benefit or burden minorities, and the Fifth Amendment's equal protection obligation equals the Fourteenth Amendment's.

Northeastern Florida Chapter of the Associated General Contractors of America v. City of Jacksonville

1993remanded

An association of contractors has standing to challenge a minority set-aside ordinance without proving any member would have won a contract absent the ordinance; the injury is denial of equal competitive opportunity, not loss of a specific contract.

Martin K. Eby Construction Company, Inc. v. Dallas Area Rapid Transit

2004enforced

A contractor must exhaust administrative remedies established by a regional transportation authority before pursuing breach of contract claims in court, even when the authority lacks governmental immunity from suit.