Evans, Mechwart, Hambleton & Tilton, Inc. v. Triad Architects, Ltd.

196 Ohio App. 3d 784 | Ohio Court of Appeals | 2011

reversedCited 2 timesSTANDARDTexas
View on Court Website

Holding Summary

Pay-when-paid clauses are timing mechanisms, not conditions precedent; the contractor must pay the subcontractor within a reasonable time regardless of owner nonpayment.

A pay-when-paid provision serves as a timing mechanism, and not a condition precedent, for payment.

Ohio Court of Appeals, 2011

Related Cases

Green International, Inc. v. Solis

1997modified

No-damages-for-delay clauses in construction contracts need not meet the conspicuousness requirement established in Dresser for exculpatory negligence clauses, and such clauses are enforceable to bar delay damages absent specific exceptions.

Associated Indemnity Corp. v. CAT Contracting, Inc.

1998modified

A surety does not owe a common law duty of good faith to its principal, but good faith is a contractual condition precedent to indemnification, requiring proof of improper motive or willful ignorance rather than mere negligence.

Rocor International, Inc. v. National Union Fire Insurance Co. of Pittsburgh

2002modified

An insured may assert an article 21.21 claim against its excess liability carrier for unfair claim settlement practices, but liability requires proof of a proper settlement demand within policy limits that an ordinarily prudent insurer would accept.

EBC, Inc. v. Clark Building System, Inc.

2010enforced

A supplier cannot enforce a payment obligation against a project owner based on a letter offering optional direct payment arrangements, where the supplier's own deposition testimony demonstrates it never understood the letter as a binding contract.

Sage Street Associates v. Northdale Construction Co.

1993remanded

Texas Constitution's usury provision applies only to lending transactions, not to judicially-awarded prejudgment interest, which derives from court order rather than commercial agreement.

Lenape Resources Corp. v. Tennessee Gas Pipeline Co.

1996enforced

Section 2.306 of the UCC does not apply to take-or-pay gas contracts where parties have specified quantity as a determinable amount (85% of delivery capacity), and good faith obligations remain applicable to increases in delivery capacity.