Hutton Contracting Co. v. City of Coffeyville

487 F.3d 772 | Court of Appeals for the Tenth Circuit | 2007

enforcedCited 23 timesBATTLE_TESTEDTexas
View on Court Website

What This Case Means for Subcontractors

Hutton Contracting built power and fiber-optic lines for the City of Coffeyville but faced delays partly caused by its supplier's late pole deliveries. The court ruled that contractors cannot use force-majeure clauses to escape responsibility for supplier delays, and that liquidated damages clauses are enforceable if they were reasonable when the contract was signed. Hutton lost $85,500 in liquidated damages even though actual damages may have differed. This matters to subcontractors because you remain liable for your suppliers' performance, and penalty clauses in your contracts will likely be enforced.

Key Takeaways

  • You are responsible for your suppliers' delays—force-majeure clauses typically won't protect you from supplier performance failures
  • Liquidated damages provisions are enforceable if they were reasonable at contract signing, regardless of whether actual damages end up being higher or lower
  • Make sure your subcontracts flow down liability for supplier delays to your suppliers, or you'll absorb the cost yourself
  • Review liquidated damages amounts carefully before signing—courts will enforce them even if they don't match real damages

A contractor is responsible for the unexcused performance failures of its subcontractor.

Court of Appeals for the Tenth Circuit, 2007

Frequently Asked Question

Can I use a force-majeure clause to avoid paying damages if my supplier is late?

No. Courts have ruled that contractors remain responsible for supplier delays even when a force-majeure clause exists. You cannot pass the blame to your supplier to escape liability to your customer. Instead, flow down the delay responsibility to your suppliers in your subcontracts so they bear the cost.

Related Cases

Gall v. United States

2007enforced

Appellate courts must review all sentences under an abuse-of-discretion standard regardless of whether they fall inside or outside the Guidelines range, and cannot require extraordinary circumstances to justify sentences outside the range.

Piotrowski v. City of Houston

2001reversed

Municipal liability under § 1983 requires proof of official policy as the moving force; isolated employee misconduct insufficient, and equal protection claim time-barred.

Adarand Constructors, Inc. v. Pena

1995remanded

Federal race-based classifications must be analyzed under strict scrutiny regardless of whether they benefit or burden minorities, and the Fifth Amendment's equal protection obligation equals the Fourteenth Amendment's.

Northeastern Florida Chapter of the Associated General Contractors of America v. City of Jacksonville

1993remanded

An association of contractors has standing to challenge a minority set-aside ordinance without proving any member would have won a contract absent the ordinance; the injury is denial of equal competitive opportunity, not loss of a specific contract.

In Re Kellogg Brown & Root, Inc.

2005enforced

The Civil Commitment of Sexually Violent Predators Act is civil, not criminal, and does not violate due process even when applied to incompetent defendants.

Edwin P. Harrison, and United States of America, Party in Interest v. Westinghouse Savannah River Company

1999reversed

The Fourth Circuit reversed the district court's dismissal, holding that the False Claims Act broadly reaches false statements made to obtain government contract approval, not just false payment claims themselves.