In re Makwa Builders, LLC

545 B.R. 311 | United States Bankruptcy Court, D. New Mexico | 2016

modifiedCited 0 timesSTANDARDTexas
View on Court Website

What This Case Means for Subcontractors

Everguard Roofing sued Makwa Builders in bankruptcy court over unpaid roofing work at a New Mexico university project. The court allowed Everguard's claim of $76,357.90, but made it contingent—meaning Everguard only gets paid if and when Makwa receives payment from the university. The court rejected Everguard's request for interest and attorney fees. This case shows that pay-if-paid clauses are enforceable in bankruptcy, but subcontractors must wait for the general contractor to get paid first.

Key Takeaways

  • Pay-if-paid clauses are legally binding in bankruptcy court—your payment depends on the GC getting paid by the owner, not on the GC's other finances
  • You cannot recover interest or attorney fees on unpaid invoices just because a contractor went bankrupt; you must prove a separate violation like the Prompt Pay Act
  • File your claim amendment early and include detailed documentation (invoices, ledgers, statements) to support your full amount—vague claims get reduced

Everguard is entitled to an allowed contingent claim under 11 U.S.C. § 502(b).

United States Bankruptcy Court, D. New Mexico, 2016

Frequently Asked Question

If my contractor goes bankrupt, can I still get paid under a pay-if-paid clause?

Yes, but only if the contractor receives payment from the project owner. Your claim becomes contingent, meaning you wait in line until money flows to the bankrupt contractor. You cannot collect interest or attorney fees simply because of the bankruptcy—you'd need to prove a separate contract violation like failure to pay within required timeframes under state law.

Related Cases

General Services Commission v. Little-Tex Insulation Co.

2001voided

The State does not waive sovereign immunity from breach-of-contract suits by accepting contract benefits; Chapter 2260's administrative procedure is the exclusive remedy for such claims.

Green International, Inc. v. Solis

1997modified

No-damages-for-delay clauses in construction contracts need not meet the conspicuousness requirement established in Dresser for exculpatory negligence clauses, and such clauses are enforceable to bar delay damages absent specific exceptions.

Associated Indemnity Corp. v. CAT Contracting, Inc.

1998modified

A surety does not owe a common law duty of good faith to its principal, but good faith is a contractual condition precedent to indemnification, requiring proof of improper motive or willful ignorance rather than mere negligence.

Italian Cowboy Partners, Ltd. v. Prudential Insurance Co. of America

2011remanded

A standard merger clause without clear and unequivocal language expressly disclaiming reliance does not bar a fraud claim, even in a commercial lease agreement between parties.

Heldenfels Bros. v. City of Corpus Christi

1992enforced

A municipality owes no duty to a subcontractor to ensure a general contractor provides valid payment bonds, and a subcontractor cannot recover from the municipality under quantum meruit, unjust enrichment, or negligence theories when the general contractor abandons the project.

Department of the Army v. Blue Fox, Inc.

1999voided

Sovereign immunity bars subcontractors from enforcing equitable liens against the United States Government, as the APA's waiver of immunity does not extend to claims for money damages.