JBC of Wyoming Corp. v. City of Cheyenne

843 P.2d 1190 | Wyoming Supreme Court | 1992

affirmedCited 30 timesBATTLE_TESTEDTexas
View on Court Website

What This Case Means for Subcontractors

JBC, a general contractor on a $20+ million pipeline project in Wyoming, went to arbitration with the City of Cheyenne over unpaid amounts. The arbitrator awarded JBC consequential damages (30% per year on unpaid sums) even though JBC never formally submitted this claim through the contract's required claims procedure. The Wyoming Supreme Court sided with the lower court and struck down the consequential damages award, ruling the arbitrator exceeded his authority by awarding damages that weren't properly submitted through the contractual process.

Key Takeaways

  • Always submit all claims—including consequential damages—through the exact procedure your contract requires, or you may lose the right to recover them even if an arbitrator initially awards them.
  • Arbitrators can only decide issues that are actually submitted to them; failing to formally present a claim type means it's off the table, regardless of the merits.
  • Document and formally notify the owner of every type of damage you're claiming (delay costs, lost productivity, financing charges, etc.) using the contract's mandated process before arbitration or litigation begins.

An arbitrator exceeds his powers when he decides matters which were not submitted to him.

Wyoming Supreme Court, 1992

Frequently Asked Question

Can an arbitrator award me damages I didn't formally claim during the dispute process?

No. An arbitrator can only decide issues actually submitted to them. If your contract requires you to submit claims through a specific procedure and you skip that step, you lose the right to recover those damages—even if the arbitrator thinks you deserve them. Always follow your contract's claims process exactly.

Related Cases

Atlantic Marine Constr. Co. v. United States Dist. Court for Western Dist. of Tex.

2013reversed

Forum-selection clauses in federal contracts are enforced through §1404(a) transfer motions, not §1406(a) dismissals, and must be given controlling weight except in exceptional circumstances.

Texas Natural Resource Conservation Commission v. IT-Davy

2002voided

Sovereign immunity bars a contractor's breach-of-contract suit against a state agency absent express legislative consent; neither the agency's conduct, contract terms, nor general statutes waive immunity from suit.

Martin K. Eby Construction Company, Inc. v. Dallas Area Rapid Transit

2004enforced

A contractor must exhaust administrative remedies established by a regional transportation authority before pursuing breach of contract claims in court, even when the authority lacks governmental immunity from suit.

Edwin P. Harrison, and United States of America, Party in Interest v. Westinghouse Savannah River Company

1999reversed

The Fourth Circuit reversed the district court's dismissal, holding that the False Claims Act broadly reaches false statements made to obtain government contract approval, not just false payment claims themselves.

General Services Commission v. Little-Tex Insulation Co.

2001voided

The State does not waive sovereign immunity from breach-of-contract suits by accepting contract benefits; Chapter 2260's administrative procedure is the exclusive remedy for such claims.

Green International, Inc. v. Solis

1997modified

No-damages-for-delay clauses in construction contracts need not meet the conspicuousness requirement established in Dresser for exculpatory negligence clauses, and such clauses are enforceable to bar delay damages absent specific exceptions.