Koch v. Construction Technology, Inc.

924 S.W.2d 68 | Tennessee Supreme Court | 1996

modifiedCited 19 timesSTANDARDTexas
View on Court Website

What This Case Means for Subcontractors

A painting subcontractor sued a general contractor over unpaid work on a Memphis housing project. The general contractor had a 'pay when paid' clause stating the subcontractor would only be paid when the general contractor received payment from the owner. The Tennessee Supreme Court ruled that 'pay when paid' clauses are timing provisions, not conditions that eliminate the general contractor's obligation to pay. The court found the clause did not shift the owner's credit risk to the subcontractor without very clear language stating that intent. This decision protects subcontractors from being left unpaid if the owner fails to pay the general contractor.

Key Takeaways

  • A 'pay when paid' clause delays payment timing but does not eliminate the general contractor's obligation to pay you—the general contractor still owes you even if the owner doesn't pay them
  • Courts disfavor conditions that shift financial risk to subcontractors; a 'pay when paid' clause must use extremely clear language to actually make your payment conditional on the owner paying the general contractor
  • Review your subcontract carefully—if it contains a 'pay when paid' clause, you likely still have a right to sue for payment even if the general contractor claims the owner hasn't paid them

Condition precedents are not favored in contract law, and will not be upheld unless there is clear language to support them.

Tennessee Supreme Court, 1996

Frequently Asked Question

If my subcontract says 'pay when paid,' can the general contractor refuse to pay me until the owner pays them?

No. A 'pay when paid' clause only delays when you get paid—it doesn't eliminate the general contractor's obligation to pay you. The general contractor cannot use the owner's non-payment as an excuse to avoid paying you unless the contract uses extremely clear language stating that your payment is conditional on the owner paying first. You can still sue for payment even if the owner hasn't paid the general contractor.

Related Cases

Green International, Inc. v. Solis

1997modified

No-damages-for-delay clauses in construction contracts need not meet the conspicuousness requirement established in Dresser for exculpatory negligence clauses, and such clauses are enforceable to bar delay damages absent specific exceptions.

Rocor International, Inc. v. National Union Fire Insurance Co. of Pittsburgh

2002modified

An insured may assert an article 21.21 claim against its excess liability carrier for unfair claim settlement practices, but liability requires proof of a proper settlement demand within policy limits that an ordinarily prudent insurer would accept.

EBC, Inc. v. Clark Building System, Inc.

2010enforced

A supplier cannot enforce a payment obligation against a project owner based on a letter offering optional direct payment arrangements, where the supplier's own deposition testimony demonstrates it never understood the letter as a binding contract.

Sage Street Associates v. Northdale Construction Co.

1993remanded

Texas Constitution's usury provision applies only to lending transactions, not to judicially-awarded prejudgment interest, which derives from court order rather than commercial agreement.

El Paso Field Services, L.P. and Gulfterra South Texas, L.P. F/K/A El Paso South Texas, L.P. v. Mastec North America, Inc. and Mastec, Inc.

2012enforced

Contract clearly allocated all risk of undiscovered foreign pipeline crossings to contractor despite owner's due diligence obligation, as contractor assumed full responsibility for site conditions notwithstanding any owner representations.

Chilton Insurance Co. v. Pate & Pate Enterprises, Inc.

1996modified

A general contractor that judicially admits owing a subcontractor a specific credit amount and continues treating the contract as valid waives its right to claim the subcontractor's breach excuses non-payment.