L & A Contracting Company v. Southern Concrete Services, Inc.

17 F.3d 106 | Court of Appeals for the Fifth Circuit | 1994

modifiedCited 157 timesFLAGSHIPFederal (5th Circuit)
View on Court Website

What This Case Means for Subcontractors

L & A Contracting sued Southern Concrete Services and its surety (performance bond company) for failing to deliver concrete on a bridge project. The court found Southern Concrete liable for breach but ruled the surety was not liable because L & A never formally declared Southern in default using clear, direct language. The surety only becomes responsible when the contractor explicitly terminates the contract and declares material breach—complaints about poor performance alone don't trigger surety liability.

Key Takeaways

  • If you're a subcontractor with a performance bond, your surety won't be liable unless the contractor formally declares you in default using explicit, unambiguous language. Vague complaints don't count.
  • If you're a general contractor, you must formally declare a bonded subcontractor in default with clear, direct language to hold the surety responsible. Document this declaration carefully.
  • There's a legal difference between 'breach' (failing to perform) and 'default' (formal termination). Only default triggers surety liability, so know your contract's default procedures.

Declaration of default must be made in clear, direct, and unequivocal language.

Court of Appeals for the Fifth Circuit, 1994

Frequently Asked Question

What do I need to do to make a bonded subcontractor's surety pay for poor performance?

You must formally declare the subcontractor in default using clear, direct, and unequivocal language that explicitly states the material breach and contract termination. Simply complaining about performance problems is not enough. The surety won't be liable unless you follow proper default procedures outlined in your contract.

Related Cases

Atlantic Marine Constr. Co. v. United States Dist. Court for Western Dist. of Tex.

2013reversed

Forum-selection clauses in federal contracts are enforced through §1404(a) transfer motions, not §1406(a) dismissals, and must be given controlling weight except in exceptional circumstances.

Texas Natural Resource Conservation Commission v. IT-Davy

2002voided

Sovereign immunity bars a contractor's breach-of-contract suit against a state agency absent express legislative consent; neither the agency's conduct, contract terms, nor general statutes waive immunity from suit.

Martin K. Eby Construction Company, Inc. v. Dallas Area Rapid Transit

2004enforced

A contractor must exhaust administrative remedies established by a regional transportation authority before pursuing breach of contract claims in court, even when the authority lacks governmental immunity from suit.

General Services Commission v. Little-Tex Insulation Co.

2001voided

The State does not waive sovereign immunity from breach-of-contract suits by accepting contract benefits; Chapter 2260's administrative procedure is the exclusive remedy for such claims.

Green International, Inc. v. Solis

1997modified

No-damages-for-delay clauses in construction contracts need not meet the conspicuousness requirement established in Dresser for exculpatory negligence clauses, and such clauses are enforceable to bar delay damages absent specific exceptions.

Moncharsh v. Heily & Blase

1992enforced

An arbitrator's decision is generally not reviewable for errors of fact or law, with limited exceptions for fraud, corruption, exceeding powers, or procedural unfairness.