Linan-Faye Construction Co. v. Housing Authority

847 F. Supp. 1191 | District Court, D. New Jersey | 1994

enforcedCited 4 timesSTANDARDTexas
View on Court Website

What This Case Means for Subcontractors

A contractor on a Camden housing renovation project sued after the owner terminated the contract for convenience. The court ruled that when a contract includes a termination-for-convenience clause, the contractor cannot recover damages for problems that happened before the termination, even if the owner was at fault. The court also said delays in formally labeling the termination don't create additional damages. This means termination-for-convenience clauses are final—they cap what you can recover.

Key Takeaways

  • If your contract has a termination-for-convenience clause, you cannot sue for damages from owner breaches or delays that occurred before termination—those claims are blocked by the clause itself.
  • Do not rely on arguing the owner delayed in formally calling it a 'termination for convenience' to recover extra damages; courts will not award damages based on labeling delays.
  • Review termination clauses carefully before signing. Understand exactly what you can recover (usually only costs incurred to date plus a small profit allowance) because you cannot claim additional damages later for pre-termination disputes.

Damages arising from pre-termination breaches are subsumed within the termination for convenience clause.

District Court, D. New Jersey, 1994

Frequently Asked Question

If the owner terminates my contract for convenience, can I sue for damages from problems that happened before the termination?

No. Courts have ruled that a termination-for-convenience clause blocks all damage claims arising from pre-termination breaches or disputes. Your recovery is limited to what the termination clause itself allows—typically costs incurred plus a small profit. You cannot sue separately for owner misconduct that occurred before the termination notice.

Related Cases

Atlantic Marine Constr. Co. v. United States Dist. Court for Western Dist. of Tex.

2013reversed

Forum-selection clauses in federal contracts are enforced through §1404(a) transfer motions, not §1406(a) dismissals, and must be given controlling weight except in exceptional circumstances.

Texas Natural Resource Conservation Commission v. IT-Davy

2002voided

Sovereign immunity bars a contractor's breach-of-contract suit against a state agency absent express legislative consent; neither the agency's conduct, contract terms, nor general statutes waive immunity from suit.

Martin K. Eby Construction Company, Inc. v. Dallas Area Rapid Transit

2004enforced

A contractor must exhaust administrative remedies established by a regional transportation authority before pursuing breach of contract claims in court, even when the authority lacks governmental immunity from suit.

General Services Commission v. Little-Tex Insulation Co.

2001voided

The State does not waive sovereign immunity from breach-of-contract suits by accepting contract benefits; Chapter 2260's administrative procedure is the exclusive remedy for such claims.

Moncharsh v. Heily & Blase

1992enforced

An arbitrator's decision is generally not reviewable for errors of fact or law, with limited exceptions for fraud, corruption, exceeding powers, or procedural unfairness.

Rory v. Continental Insurance

2005enforced

Unambiguous contractual limitations periods in insurance policies must be enforced as written unless they violate law or public policy; judicial assessments of reasonableness cannot override clear contract terms.