Nance v. Resolution Trust Corp.

803 S.W.2d 323 | Texas Court of Appeals, 4th District (San Antonio) | 1990

modifiedCited 30 timesBATTLE_TESTEDTexas
View on Court Website

What This Case Means for Subcontractors

A general partner sued his lender (Alamo Savings) for refusing to fund a construction loan. The jury found the lender breached the contract and awarded $993,000 in damages. However, the court threw out the verdict, ruling that the lender had a clear contractual right to withhold 10% retainage and that the damages claim lacked sufficient proof of actual losses. The lender won its counterclaim for the unpaid loan balance.

Key Takeaways

  • Retainage clauses in loan agreements are enforceable—lenders can legally withhold funds if the contract explicitly allows it. Review your loan documents carefully before work begins.
  • Claiming lost profits as damages requires solid proof of what you actually would have earned. Vague or speculative damage estimates will be rejected by courts.
  • If your lender withholds funds under a contract clause, you cannot automatically claim breach. You must prove the lender acted outside its contractual rights or violated good faith obligations.

Section 4.02 of the loan agreement clearly gave Alamo the right to withhold 10% retainage.

Texas Court of Appeals, 4th District (San Antonio), 1990

Frequently Asked Question

Can a lender legally withhold 10% of my construction loan funds as retainage?

Yes, if your loan agreement explicitly gives the lender that right. Courts will enforce retainage clauses as written. However, the lender must still act in good faith and cannot use retainage as a pretext to breach other obligations. Always review retainage terms before signing.

Related Cases

Texas Natural Resource Conservation Commission v. IT-Davy

2002voided

Sovereign immunity bars a contractor's breach-of-contract suit against a state agency absent express legislative consent; neither the agency's conduct, contract terms, nor general statutes waive immunity from suit.

Martin K. Eby Construction Company, Inc. v. Dallas Area Rapid Transit

2004enforced

A contractor must exhaust administrative remedies established by a regional transportation authority before pursuing breach of contract claims in court, even when the authority lacks governmental immunity from suit.

Edwin P. Harrison, and United States of America, Party in Interest v. Westinghouse Savannah River Company

1999reversed

The Fourth Circuit reversed the district court's dismissal, holding that the False Claims Act broadly reaches false statements made to obtain government contract approval, not just false payment claims themselves.

Green International, Inc. v. Solis

1997modified

No-damages-for-delay clauses in construction contracts need not meet the conspicuousness requirement established in Dresser for exculpatory negligence clauses, and such clauses are enforceable to bar delay damages absent specific exceptions.

Heldenfels Bros. v. City of Corpus Christi

1992enforced

A municipality owes no duty to a subcontractor to ensure a general contractor provides valid payment bonds, and a subcontractor cannot recover from the municipality under quantum meruit, unjust enrichment, or negligence theories when the general contractor abandons the project.

Flameout Design & Fabrication, Inc. v. Pennzoil Caspian Corp.

1999enforced

Summary judgment for defendants was properly granted because Flameout failed to satisfy the statute of frauds for an alleged three-year contract, as the three documents cited did not constitute a signed, enforceable written agreement for the sale of goods.