PSE Consulting, Inc. v. Mercede

267 Conn. 279 | Supreme Court of Connecticut | 2004

enforcedCited 85 timesBATTLE_TESTEDTexas
View on Court Website

What This Case Means for Subcontractors

A surety company (National Fire Insurance) tried to recover indemnification payments it made to settle a claim under a payment bond. The court ruled that even though the indemnity agreement favored the surety, the surety must still act in good faith when making settlement payments. The surety lost because evidence showed it settled the claim improperly and in bad faith, meaning subcontractors and sureties cannot hide behind broad indemnity language to avoid accountability for unfair settlement practices.

Key Takeaways

  • Broad indemnity clauses in surety agreements do not give sureties unlimited power to settle claims—good faith is always required, even when the contract says otherwise
  • If a surety settles a claim against your bond without proper investigation or fair dealing, you can sue for breach of the implied covenant of good faith and recover damages
  • Document everything about how a surety handles your bond claim; if settlement looks rushed or unfair, gather evidence immediately because you may need to prove bad faith

Surety's discretion to settle is not unfettered; surety entitled to indemnification only for good faith payments.

Supreme Court of Connecticut, 2004

Frequently Asked Question

Can a surety company settle a claim against my bond however it wants if the indemnity agreement gives it broad power?

No. Even with a broad indemnity clause, a surety must act in good faith when settling claims. If the surety settles improperly or unfairly, you can sue for damages for breach of good faith and fair dealing. The court will look at whether the surety actually investigated the claim and dealt fairly with you.

Related Cases

Atlantic Marine Constr. Co. v. United States Dist. Court for Western Dist. of Tex.

2013reversed

Forum-selection clauses in federal contracts are enforced through §1404(a) transfer motions, not §1406(a) dismissals, and must be given controlling weight except in exceptional circumstances.

Texas Natural Resource Conservation Commission v. IT-Davy

2002voided

Sovereign immunity bars a contractor's breach-of-contract suit against a state agency absent express legislative consent; neither the agency's conduct, contract terms, nor general statutes waive immunity from suit.

Martin K. Eby Construction Company, Inc. v. Dallas Area Rapid Transit

2004enforced

A contractor must exhaust administrative remedies established by a regional transportation authority before pursuing breach of contract claims in court, even when the authority lacks governmental immunity from suit.

Fitzgerald v. Advanced Spine Fixation Systems, Inc.

1999enforced

A manufacturer must indemnify an innocent seller for products liability litigation costs under Texas Civil Practice & Remedies Code § 82.002(a), even if the seller did not sell the particular defective product that injured the plaintiff, provided the seller qualifies as a 'seller' under the statute.

General Services Commission v. Little-Tex Insulation Co.

2001voided

The State does not waive sovereign immunity from breach-of-contract suits by accepting contract benefits; Chapter 2260's administrative procedure is the exclusive remedy for such claims.

Green International, Inc. v. Solis

1997modified

No-damages-for-delay clauses in construction contracts need not meet the conspicuousness requirement established in Dresser for exculpatory negligence clauses, and such clauses are enforceable to bar delay damages absent specific exceptions.