Sage Street Associates v. Northdale Construction Co.

863 S.W.2d 438 | Texas Supreme Court | 1993

remandedCited 270 timesFLAGSHIPTexas
View on Court Website

What This Case Means for Subcontractors

Sage Street Associates disputed a 10% prejudgment interest rate awarded by a court in a construction contract dispute, claiming Texas's usury law capped it at 6%. The Texas Supreme Court ruled that the state's constitutional usury limits don't apply to interest ordered by judges—only to commercial lending agreements. This means courts have flexibility to award prejudgment interest at rates higher than the usury cap when deciding construction disputes.

Key Takeaways

  • Court-ordered prejudgment interest is not subject to Texas usury limits, so judges can award rates above 6% if they find it appropriate for your case
  • Usury protections only apply to lending transactions between parties, not to judicial remedies for breach of contract
  • If you're owed money from a construction contract dispute, the interest rate a judge awards won't be capped by constitutional lending restrictions

Article XVI, section 11 is inapplicable to the rate of prejudgment interest set by a court.

Texas Supreme Court, 1993

Frequently Asked Question

Can a court award me more than 6% interest on money owed to me in a construction contract dispute?

Yes. Texas courts can award prejudgment interest above the 6% usury limit because court-ordered interest comes from a judge's decision, not a lending agreement. The constitutional usury cap only restricts commercial lending between parties, not judicial remedies for breach of contract.

Related Cases

Texas Natural Resource Conservation Commission v. IT-Davy

2002voided

Sovereign immunity bars a contractor's breach-of-contract suit against a state agency absent express legislative consent; neither the agency's conduct, contract terms, nor general statutes waive immunity from suit.

Martin K. Eby Construction Company, Inc. v. Dallas Area Rapid Transit

2004enforced

A contractor must exhaust administrative remedies established by a regional transportation authority before pursuing breach of contract claims in court, even when the authority lacks governmental immunity from suit.

Edwin P. Harrison, and United States of America, Party in Interest v. Westinghouse Savannah River Company

1999reversed

The Fourth Circuit reversed the district court's dismissal, holding that the False Claims Act broadly reaches false statements made to obtain government contract approval, not just false payment claims themselves.

Green International, Inc. v. Solis

1997modified

No-damages-for-delay clauses in construction contracts need not meet the conspicuousness requirement established in Dresser for exculpatory negligence clauses, and such clauses are enforceable to bar delay damages absent specific exceptions.

Heldenfels Bros. v. City of Corpus Christi

1992enforced

A municipality owes no duty to a subcontractor to ensure a general contractor provides valid payment bonds, and a subcontractor cannot recover from the municipality under quantum meruit, unjust enrichment, or negligence theories when the general contractor abandons the project.

Flameout Design & Fabrication, Inc. v. Pennzoil Caspian Corp.

1999enforced

Summary judgment for defendants was properly granted because Flameout failed to satisfy the statute of frauds for an alleged three-year contract, as the three documents cited did not constitute a signed, enforceable written agreement for the sale of goods.