STEWARD MACH. CO., INC. v. White Oak Corp.

462 F. Supp. 2d 251 | District Court, D. Connecticut | 2006

enforcedCited 0 timesSTANDARDTexas
View on Court Website

What This Case Means for Subcontractors

Steward Machine Company supplied machinery to White Oak Corp. for a Connecticut bridge project but wasn't paid in full and had to store the equipment for years. The court ruled that White Oak must pay Steward for both the machinery and storage costs. The key finding: White Oak's payment obligation to Steward was not dependent on whether the state (ConnDOT) paid White Oak first. This protects subcontractors from being caught in payment chain delays.

Key Takeaways

  • Your right to payment from the general contractor does not depend on the GC receiving payment from the project owner—get this in writing in your contract
  • You can recover storage and holding costs if a GC fails to accept delivery or pay on time—document all storage expenses carefully
  • A written purchase order contract is strong evidence of payment obligations and will be enforced even if the GC claims it's waiting for owner payment

Payment by ConnDOT was not a prerequisite to White Oak's obligation.

District Court, D. Connecticut, 2006

Frequently Asked Question

Can a general contractor refuse to pay me because the project owner hasn't paid them yet?

No. This case confirms that your payment obligation from the GC is separate from their payment from the owner. The GC cannot use delayed owner payment as an excuse to withhold your money. Make sure your contract clearly states payment terms are not conditional on the GC receiving funds from above.

Related Cases

Atlantic Marine Constr. Co. v. United States Dist. Court for Western Dist. of Tex.

2013reversed

Forum-selection clauses in federal contracts are enforced through §1404(a) transfer motions, not §1406(a) dismissals, and must be given controlling weight except in exceptional circumstances.

Texas Natural Resource Conservation Commission v. IT-Davy

2002voided

Sovereign immunity bars a contractor's breach-of-contract suit against a state agency absent express legislative consent; neither the agency's conduct, contract terms, nor general statutes waive immunity from suit.

Martin K. Eby Construction Company, Inc. v. Dallas Area Rapid Transit

2004enforced

A contractor must exhaust administrative remedies established by a regional transportation authority before pursuing breach of contract claims in court, even when the authority lacks governmental immunity from suit.

Edwin P. Harrison, and United States of America, Party in Interest v. Westinghouse Savannah River Company

1999reversed

The Fourth Circuit reversed the district court's dismissal, holding that the False Claims Act broadly reaches false statements made to obtain government contract approval, not just false payment claims themselves.

General Services Commission v. Little-Tex Insulation Co.

2001voided

The State does not waive sovereign immunity from breach-of-contract suits by accepting contract benefits; Chapter 2260's administrative procedure is the exclusive remedy for such claims.

Green International, Inc. v. Solis

1997modified

No-damages-for-delay clauses in construction contracts need not meet the conspicuousness requirement established in Dresser for exculpatory negligence clauses, and such clauses are enforceable to bar delay damages absent specific exceptions.