Textron Defense Systems v. Sheila E. Widnall, Secretary of the Air Force

143 F.3d 1465 | Court of Appeals for the Federal Circuit | 1998

enforcedCited 76 timesBATTLE_TESTEDTexas
View on Court Website

What This Case Means for Subcontractors

Textron contracted with the Air Force on a cost-plus-award-fee research project. When the Air Force terminated the contract for convenience before completion, Textron claimed it deserved a partial share of the unearned award fees. The Federal Circuit Court ruled against Textron, holding that the contract's award fee clause was explicitly exempted from the termination clause. This means Textron got only what it earned—no payment for work it never performed.

Key Takeaways

  • Award fee clauses can be written to exclude termination protections. Review your contract language carefully to see if fees are protected or excluded when work stops.
  • You cannot claim payment for unperformed work, even on cost-plus contracts. The contract's plain language controls, not your expectations about what you might have earned.
  • Incremental funding and contract modifications do not guarantee future payments. Each funding allotment is separate, and termination cuts off all unearned compensation unless the contract explicitly protects it.

The plain language of the contract clearly exempts the Award Fee from the Termination clause.

Court of Appeals for the Federal Circuit, 1998

Frequently Asked Question

If my contract is terminated for convenience, can I get paid for award fees I didn't earn yet?

Not if your contract exempts the award fee from the termination clause. Courts enforce the plain language of the contract. You are only entitled to fees you actually earned through completed work. Always check whether your award fee clause is protected or excluded from termination provisions before signing.

Related Cases

General Services Commission v. Little-Tex Insulation Co.

2001voided

The State does not waive sovereign immunity from breach-of-contract suits by accepting contract benefits; Chapter 2260's administrative procedure is the exclusive remedy for such claims.

PYCA Industries, Inc. v. Harrison County Waste Water Management District

1996modified

A wastewater district is a citizen for diversity jurisdiction purposes and a political subdivision entitled to sovereign immunity from tort claims under pre-Pruett Mississippi law.

MCI CONSTRUCTORS, LLC v. City of Greensboro

2010enforced

District court properly confirmed arbitration award finding City entitled to $14.9 million damages; arbitration panel did not exceed its powers and award was not procured by undue means.

Linan-Faye Construction Co., Inc. v. Housing Authority of the City of Camden

1995remanded

District court erred in applying federal common law instead of New Jersey law to interpret the termination for convenience clause, but New Jersey courts would look to federal common law for guidance on this issue.

Blackstone Medical, Inc. D/B/A Orthofix Spinal Implants v. Phoenix Surgicals, LLC

2015enforced

Trial court properly denied motions for directed verdict and judgment notwithstanding the verdict on breach of contract and promissory estoppel claims where evidence supported jury findings of wrongful termination and waiver of exclusivity provision.

Lafarge Corp. v. Wolff, Inc.

1998remanded

A contract provision stating the owner need not continue plant operation does not permit unilateral termination upon sale; the jury properly found the parties intended the contract to survive the sale, and damages must be recalculated to account for avoided costs of performance.