United States Ex Rel. Accoustical Concepts, Inc. v. Travelers Casualty & Surety Co. of America

635 F. Supp. 2d 434 | District Court, E.D. Virginia | 2009

enforcedCited 1 timesSTANDARDTexas
View on Court Website

What This Case Means for Subcontractors

A subcontractor sued a surety company on a Miller Act payment bond for work on federal projects. The surety tried to offset what it owed by using debts the subcontractor owed on unrelated non-federal projects. The court ruled that sureties cannot use setoff clauses to delay payment on federal work, because the Miller Act requires prompt payment to subcontractors regardless of disputes on other jobs.

Key Takeaways

  • Setoff clauses in your subcontract cannot be used to withhold payment for federal project work, even if you owe money on other projects
  • The Miller Act protects your right to prompt payment on federal jobs—sureties must pay you for completed federal work without delay
  • If a general contractor tries to offset federal project payments with claims from non-federal projects, you have grounds to sue the surety directly

Setoff provisions contravene the Miller Act's purpose of providing prompt payment to subcontractors.

District Court, E.D. Virginia, 2009

Frequently Asked Question

Can a general contractor withhold my payment on a federal project because I owe them money on a different job?

No. Under the Miller Act, sureties cannot use setoff clauses to delay payment for federal construction work, even if you have debts on unrelated projects. The law requires prompt payment for federal work regardless of disputes elsewhere. You can sue the surety directly if payment is wrongfully withheld.

Related Cases

Green International, Inc. v. Solis

1997modified

No-damages-for-delay clauses in construction contracts need not meet the conspicuousness requirement established in Dresser for exculpatory negligence clauses, and such clauses are enforceable to bar delay damages absent specific exceptions.

Heldenfels Bros. v. City of Corpus Christi

1992enforced

A municipality owes no duty to a subcontractor to ensure a general contractor provides valid payment bonds, and a subcontractor cannot recover from the municipality under quantum meruit, unjust enrichment, or negligence theories when the general contractor abandons the project.

Department of the Army v. Blue Fox, Inc.

1999voided

Sovereign immunity bars subcontractors from enforcing equitable liens against the United States Government, as the APA's waiver of immunity does not extend to claims for money damages.

Rocor International, Inc. v. National Union Fire Insurance Co. of Pittsburgh

2002modified

An insured may assert an article 21.21 claim against its excess liability carrier for unfair claim settlement practices, but liability requires proof of a proper settlement demand within policy limits that an ordinarily prudent insurer would accept.

Weize Co. v. Colorado Regional Construction, Inc.

2010affirmed

A general contractor violated Colorado's construction trust fund statute by failing to hold funds in trust for subcontractors and suppliers, and a lien release bond does not exempt contractors from trust fund obligations or excuse failure to record a lis pendens.

Rice v. Pinney

2001enforced

A county court has jurisdiction to determine immediate possession in a forcible detainer action even when a concurrent district court suit challenges title, provided the possession determination does not necessarily require resolving the title dispute.