United States ex rel. Benefit of Walton Technology, Inc. v. Weststar Engineering, Inc.

290 F.3d 1199 | Court of Appeals for the Ninth Circuit | 2002

remandedCited 0 timesSTANDARDTexas
View on Court Website

What This Case Means for Subcontractors

Walton Technology, a subcontractor on a federal project, sued for unpaid equipment rental fees. The subcontract contained a 'pay when and if paid' clause stating Walton would only get paid after the prime contractor received payment from the government. The Ninth Circuit ruled that such clauses do not automatically waive a subcontractor's rights under the Miller Act, which guarantees payment for work on federal projects. The court sent the case back for trial, rejecting the surety's argument that the unpaid clause excused them from liability.

Key Takeaways

  • A 'pay when and if paid' clause in your subcontract does not eliminate your Miller Act payment bond rights—courts require a clear, explicit waiver to remove those protections
  • If the prime contractor hasn't been paid by the government, you may still have a valid claim against the Miller Act surety bond; don't assume you're out of luck
  • Document everything about payment terms in writing and push back on vague 'pay when paid' language—courts scrutinize these clauses closely and interpret them against the drafter

Pay when and if paid clause does not constitute clear and explicit waiver of Miller Act rights.

Court of Appeals for the Ninth Circuit, 2002

Frequently Asked Question

If my subcontract says I only get paid 'when and if' the prime contractor gets paid, can I still claim against the Miller Act bond?

Yes. Courts have ruled that 'pay when and if paid' clauses do not automatically waive your Miller Act rights unless the waiver is clear and explicit. You can still pursue a claim against the surety bond even if the prime contractor hasn't received payment from the government. Always consult an attorney about your specific contract language.

Related Cases

Atlantic Marine Constr. Co. v. United States Dist. Court for Western Dist. of Tex.

2013reversed

Forum-selection clauses in federal contracts are enforced through §1404(a) transfer motions, not §1406(a) dismissals, and must be given controlling weight except in exceptional circumstances.

Texas Natural Resource Conservation Commission v. IT-Davy

2002voided

Sovereign immunity bars a contractor's breach-of-contract suit against a state agency absent express legislative consent; neither the agency's conduct, contract terms, nor general statutes waive immunity from suit.

Martin K. Eby Construction Company, Inc. v. Dallas Area Rapid Transit

2004enforced

A contractor must exhaust administrative remedies established by a regional transportation authority before pursuing breach of contract claims in court, even when the authority lacks governmental immunity from suit.

General Services Commission v. Little-Tex Insulation Co.

2001voided

The State does not waive sovereign immunity from breach-of-contract suits by accepting contract benefits; Chapter 2260's administrative procedure is the exclusive remedy for such claims.

Green International, Inc. v. Solis

1997modified

No-damages-for-delay clauses in construction contracts need not meet the conspicuousness requirement established in Dresser for exculpatory negligence clauses, and such clauses are enforceable to bar delay damages absent specific exceptions.

Moncharsh v. Heily & Blase

1992enforced

An arbitrator's decision is generally not reviewable for errors of fact or law, with limited exceptions for fraud, corruption, exceeding powers, or procedural unfairness.