United States Ex Rel. J.H. Lynch & Sons, Inc. v. Travelers Casualty & Surety Co. of America

783 F. Supp. 2d 294 | District Court, D. Rhode Island | 2011

enforcedCited 1 timesSTANDARDTexas
View on Court Website

What This Case Means for Subcontractors

J.H. Lynch & Sons, a subcontractor on a Navy project, sued the general contractor's surety for unpaid work totaling over $575,000. The general contractor had included a pay-when-paid clause in the subcontract, which the surety argued blocked Lynch's claim. The court rejected this argument and ruled that pay-when-paid clauses cannot prevent subcontractors from pursuing Miller Act claims against sureties. This decision protects subcontractors' federal payment bond rights regardless of what their subcontracts say.

Key Takeaways

  • Pay-when-paid clauses in your subcontract cannot stop you from suing the payment bond surety under the Miller Act—your federal rights override contract language
  • If you work on a federal project and don't get paid, pursue the surety directly; don't let the general contractor hide behind contract terms
  • Document all work completion dates and unpaid invoices carefully, as these are critical to proving your Miller Act claim against the surety

A pay-when-paid clause does not foreclose a subcontractor's Miller Act claim.

District Court, D. Rhode Island, 2011

Frequently Asked Question

Can a pay-when-paid clause in my subcontract prevent me from suing the surety for unpaid work?

No. This court ruled that pay-when-paid clauses do not block Miller Act claims against sureties. Your right to pursue the payment bond is a federal right that cannot be taken away by contract language between you and the general contractor or subcontractor above you. If you complete work on a federal project and aren't paid, you can still sue the surety directly.

Related Cases

Atlantic Marine Constr. Co. v. United States Dist. Court for Western Dist. of Tex.

2013reversed

Forum-selection clauses in federal contracts are enforced through §1404(a) transfer motions, not §1406(a) dismissals, and must be given controlling weight except in exceptional circumstances.

Texas Natural Resource Conservation Commission v. IT-Davy

2002voided

Sovereign immunity bars a contractor's breach-of-contract suit against a state agency absent express legislative consent; neither the agency's conduct, contract terms, nor general statutes waive immunity from suit.

Martin K. Eby Construction Company, Inc. v. Dallas Area Rapid Transit

2004enforced

A contractor must exhaust administrative remedies established by a regional transportation authority before pursuing breach of contract claims in court, even when the authority lacks governmental immunity from suit.

General Services Commission v. Little-Tex Insulation Co.

2001voided

The State does not waive sovereign immunity from breach-of-contract suits by accepting contract benefits; Chapter 2260's administrative procedure is the exclusive remedy for such claims.

Green International, Inc. v. Solis

1997modified

No-damages-for-delay clauses in construction contracts need not meet the conspicuousness requirement established in Dresser for exculpatory negligence clauses, and such clauses are enforceable to bar delay damages absent specific exceptions.

Moncharsh v. Heily & Blase

1992enforced

An arbitrator's decision is generally not reviewable for errors of fact or law, with limited exceptions for fraud, corruption, exceeding powers, or procedural unfairness.