United States For The Use And Benefit Of Walton Technology, Inc. v. Weststar Engineering, Inc.

290 F.3d 1199 | Court of Appeals for the Ninth Circuit | 2002

remandedCited 7 timesSTANDARDTexas
View on Court Website

What This Case Means for Subcontractors

Walton Technology, a subcontractor, rented equipment to the prime contractor Weststar on a federal construction project but wasn't paid. The contract had a 'pay when and if paid' clause, which Weststar argued meant Walton couldn't sue until the government paid Weststar. The Ninth Circuit ruled that this clause doesn't eliminate a subcontractor's rights under the Miller Act payment bond. Subcontractors can sue the surety for payment even if the prime contractor hasn't been paid by the government.

Key Takeaways

  • A 'pay when and if paid' clause in your subcontract does not waive your Miller Act rights—you can still sue the payment bond surety directly
  • You do not have to wait for the government to pay the prime contractor before filing a Miller Act claim against the surety
  • Document all work, equipment rental, and delivery carefully to support your Miller Act claim if payment is withheld

A subcontractor need not await government payment before initiating Miller Act action.

Court of Appeals for the Ninth Circuit, 2002

Frequently Asked Question

If my subcontract says 'pay when and if paid,' can I still sue the payment bond surety if the prime contractor doesn't pay me?

Yes. A 'pay when and if paid' clause does not eliminate your Miller Act rights. You can sue the surety directly without waiting for the government to pay the prime contractor. The clause must be very clear and explicit to waive Miller Act protections, and courts interpret it narrowly in your favor.

Related Cases

Atlantic Marine Constr. Co. v. United States Dist. Court for Western Dist. of Tex.

2013reversed

Forum-selection clauses in federal contracts are enforced through §1404(a) transfer motions, not §1406(a) dismissals, and must be given controlling weight except in exceptional circumstances.

Texas Natural Resource Conservation Commission v. IT-Davy

2002voided

Sovereign immunity bars a contractor's breach-of-contract suit against a state agency absent express legislative consent; neither the agency's conduct, contract terms, nor general statutes waive immunity from suit.

Martin K. Eby Construction Company, Inc. v. Dallas Area Rapid Transit

2004enforced

A contractor must exhaust administrative remedies established by a regional transportation authority before pursuing breach of contract claims in court, even when the authority lacks governmental immunity from suit.

General Services Commission v. Little-Tex Insulation Co.

2001voided

The State does not waive sovereign immunity from breach-of-contract suits by accepting contract benefits; Chapter 2260's administrative procedure is the exclusive remedy for such claims.

Green International, Inc. v. Solis

1997modified

No-damages-for-delay clauses in construction contracts need not meet the conspicuousness requirement established in Dresser for exculpatory negligence clauses, and such clauses are enforceable to bar delay damages absent specific exceptions.

Moncharsh v. Heily & Blase

1992enforced

An arbitrator's decision is generally not reviewable for errors of fact or law, with limited exceptions for fraud, corruption, exceeding powers, or procedural unfairness.