United States of America for the Use and Benefit of T.M.S. Mechanical Contractors, Inc., Cross-Appellee v. Millers Mutual Fire Insurance Company of Texas, Third-Party Cross-Appellant v. The Craftsmen, Inc., Third-Party and Joseph Breedlove, J.D. Richmond, Jr. And Doris D. Richmond, Third-Party

942 F.2d 946 | Court of Appeals for the Third Circuit | 1991

modifiedCited 21 timesBATTLE_TESTEDTexas
View on Court Website

What This Case Means for Subcontractors

T.M.S. Mechanical Contractors, a subcontractor on a VA hospital project, sued the Miller Act surety for Millers Mutual Fire Insurance after the general contractor delayed and then terminated the work. The court ruled that subcontractors can recover actual out-of-pocket costs for labor and materials caused by delay, but cannot recover termination costs or lost profits. This case clarifies what damages are recoverable under Miller Act bonds when projects are delayed or terminated.

Key Takeaways

  • You can recover extra costs for labor and materials directly caused by project delays under a Miller Act surety bond claim.
  • You cannot recover termination costs, demobilization fees, or lost profits on delayed work—only actual increased out-of-pocket expenses.
  • Document all delay-related costs carefully with dates and amounts to prove they were caused by the delay, not other factors.

Subcontractor can recover increased out-of-pocket costs for labor and materials caused by delay.

Court of Appeals for the Third Circuit, 1991

Frequently Asked Question

Can I recover termination costs and lost profits from a Miller Act surety bond when a project is delayed or terminated?

No. You can only recover actual out-of-pocket costs for labor and materials that were directly caused by the delay. Termination costs, demobilization expenses, and lost profits are not recoverable under Miller Act surety claims. Focus your claim on documented increases in labor and material costs that resulted from the delay itself.

Related Cases

General Services Commission v. Little-Tex Insulation Co.

2001voided

The State does not waive sovereign immunity from breach-of-contract suits by accepting contract benefits; Chapter 2260's administrative procedure is the exclusive remedy for such claims.

Green International, Inc. v. Solis

1997modified

No-damages-for-delay clauses in construction contracts need not meet the conspicuousness requirement established in Dresser for exculpatory negligence clauses, and such clauses are enforceable to bar delay damages absent specific exceptions.

Rocor International, Inc. v. National Union Fire Insurance Co. of Pittsburgh

2002modified

An insured may assert an article 21.21 claim against its excess liability carrier for unfair claim settlement practices, but liability requires proof of a proper settlement demand within policy limits that an ordinarily prudent insurer would accept.

EBC, Inc. v. Clark Building System, Inc.

2010enforced

A supplier cannot enforce a payment obligation against a project owner based on a letter offering optional direct payment arrangements, where the supplier's own deposition testimony demonstrates it never understood the letter as a binding contract.

Sage Street Associates v. Northdale Construction Co.

1993remanded

Texas Constitution's usury provision applies only to lending transactions, not to judicially-awarded prejudgment interest, which derives from court order rather than commercial agreement.

El Paso Field Services, L.P. and Gulfterra South Texas, L.P. F/K/A El Paso South Texas, L.P. v. Mastec North America, Inc. and Mastec, Inc.

2012enforced

Contract clearly allocated all risk of undiscovered foreign pipeline crossings to contractor despite owner's due diligence obligation, as contractor assumed full responsibility for site conditions notwithstanding any owner representations.